Basingstoke Re-Signalling Stage 3

Acting as direct installation resource to Network Rail for all Signalling work associated with this project covering 18 miles of re-modelling. Rail Tech have a direct onsite management presence in place who are integrated within a Network Rail project team and stores facility. Final commissioning is due in April 2010. Total of 29 staff present on-site with a project output of 5,000 hours to date.

Client

Network Rail

Project Value

£1.2 million approx

Duration

June 2009 – April 2010

Activities Undertaken

Installation of 3x Solid State Interlockings
Cable diversion works in 150 location cases.
Installation of TPWS fitments x(20)
Termination of LED Signal Heads x(80)
Installation of Impeedance Bonds x(149)
Installation of 180xTI21 and 27xHVI Tracks
AWS Installation x(76)
Installation of 77xSPT’s
Termination of Power and Lineside Cables